[Mock Test] Construction Project and Management Mock test – 1 || Civil Engineering Online tests




Welcome to your Construction Project and Managment Mock test - 1
Take an exciting test in Construction and Project Management Mock tests 
You have only 20 mins to complete the test (25 Questions)
Wish you all the best!!!
Name
Email
1.

Critical path method

1 out of 25
2.

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

2 out of 25
3.

A critical ratio scheduling

3 out of 25
4.

Updating may result in

4 out of 25
5.

Preliminary project report for a road project must contain

5 out of 25
6.

Pick up the correct statement from the following

6 out of 25
7.

Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

7 out of 25
8.

For the network shown in the given figure, the expected time for the activity

8 out of 25
9.

A golden rule for the procurement of construction stones, suggests

9 out of 25
10.

In resources levelling

10 out of 25
11.

Grader is used mainly for

11 out of 25
12.

In PERT analysis, the time estimates of activities and probability of their occurrence follow

12 out of 25
13.

Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?

13 out of 25
14.

Which of the following does not represent an activity?

14 out of 25
15.

At a work site, statistical quality control of concrete means

15 out of 25
16.

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5,  17 and 8 days respectively, The expected time is

16 out of 25
17.

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

17 out of 25
18.

Which of the following earth moving machines has the shortest cycle time?

18 out of 25
19.

Free float is mainly used to

19 out of 25
20.

During the construction period, price variation clause in contracts caters to

20 out of 25
21.

Sensitivity analysis is a study of

21 out of 25
22.

In time-cost optimization of a project, crashing is done.

22 out of 25
23.

If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be

23 out of 25
24.

The time with which direct cost does not reduce with the increase in time is known as

24 out of 25
25.

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

25 out of 25







[NPTEL Notes PDF] Civil Engineering (105 Courses in PDF Format)

Ships within 5 days | ₹ 1,250 Only.

This is the one time cost you spend for getting very good quality notes PDF for preparing any kind of Competitive exams. 

Subscribe and get the latest posts and study materials to your mail!

Enter your email address:

Delivered by FeedBurner

Those who are subscribed our web, kindly verify your mail received by you. Those who are verified, kindly ignore this message.

// hide the meta tag generator from head and rss function disable_meta_generator() { return ''; } add_filter('the_generator','disable_meta_generator'); remove_action('wp_head', 'wp_generator');