1. The foundation in which a cantilever beam is provided to join two footings, is known as
2. The additional piles which are driven to increase the capacity of supporting loads on vertical piles, are known
3. The strength of brick masonry in 1:6 cement mortar, is
4. Ornamental moulded course placed on the top of a wall, is
5. The process of making the back ground rough, before plastering, is
6. The concrete slump recommended for beams and slabs; is
7. The form work from the sides of beams can be removed only after
8. Pick up the incorrect statement from the following:
9. Nogging of a common wooden partition is
10. Pick up the incorrect statement from the following:
11. Queen closer may be placed
12. The least bearing capacity of soil is that of
13. The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than
14. The range of spread from the wall base to outer edge of a brick work foundation does not exceed
15. Pick up the incorrect statement from the following:
16. The maximum permissible differential settlement, in case of foundations in clayey soil, is usually  limited to
17. While designing a stair, the product of rise and going is approximately kept equal to
18. To construct a 10 cm thick partition wall, you will prefer
19. For brick construction, the lime-sand mortar, is
20. The bearing capacity of a water logged soil, may be improved by
21. The 9 cm × 9 cm side of a brick as seen in the wall face, is generally known a
22. Bearing capacity of soils cannot be improved by
23. The pile which is provided with a bulb filled with concrete at its lower end, is known as
24. A cut in frame of a door to receive the shutter, is called
25. Stud(s) of a common wooden partition



Share to all

Be the first to comment on "SSC JE Civil Preliminary Exam in January 2018 | Practice test Day – 53"

Leave a comment

Your email address will not be published.


*


RRB JE Civil Engineering Ebook Pdf

Total MCQs :15000
Total Pages :2279
Total Size :37 Mb
Check Sample file : Download It

Please Ensure the Speedy net for Quick download


Subscribe and get the latest posts and study materials to your mail!

Enter your email address:

Delivered by FeedBurner

// hide the meta tag generator from head and rss function disable_meta_generator() { return ''; } add_filter('the_generator','disable_meta_generator'); remove_action('wp_head', 'wp_generator');