SSC JE Civil Engineering Preliminary Exam in January 2018 | Practice test Day – 42



Welcome to your SSC JE Civil Engineering 2018 Objective Exam Practice test Day - 42
Take an exciting test in SSC JE Civil Preliminary Exam in January 2018. 
You have only 20 mins to complete the test (25 Questions)
Wish you all the best!!!
Name
Email
1. Updating may result in
2. A golden rule for the procurement of construction stones, suggests
3. Preliminary project report for a road project must contain
4. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
5. If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
6. Which of the following earth moving machines has the shortest cycle time?
7. For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
8. At a work site, statistical quality control of concrete means
9. Grader is used mainly for
10. A critical ratio scheduling
11. Free float is mainly used to
12. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
13. For the network shown in the given figure, the expected time for the activity

14. The time with which direct cost does not reduce with the increase in time is known as
15. Critical path method
16. Which of the following does not represent an activity?
17. Pick up the correct statement from the following
18. Sensitivity analysis is a study of
19. In resources levelling
20. In PERT analysis, the time estimates of activities and probability of their occurrence follow
21. Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
22. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5,  17 and 8 days respectively, The expected time is
23. In time-cost optimization of a project, crashing is done.
24. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
25. During the construction period, price variation clause in contracts caters to






Share to all

Be the first to comment on "SSC JE Civil Engineering Preliminary Exam in January 2018 | Practice test Day – 42"

Leave a comment

Your email address will not be published.


*


Subscribe and get the latest posts and study materials to your mail!

Enter your email address:

Delivered by FeedBurner

// hide the meta tag generator from head and rss function disable_meta_generator() { return ''; } add_filter('the_generator','disable_meta_generator'); remove_action('wp_head', 'wp_generator');