Estimation & Quantity surveying Mock tests - 1 || Civil Engineering Mock tests - CIVIL ENGINEERING OBJECTIVE

Estimation & Quantity surveying Mock tests – 1 || Civil Engineering Mock tests




Welcome to your Estimation and Quantity Surveying Mock test - 1
Take an exciting test in Estimation and Quantity surveying
You have only 20 mins to complete the test (25 Questions)
Wish you all the best!!!
Name
Email
1. The measurement is made in square metre in case of
2. The area of the cross-section of a road fully in banking shown in the given figure, is

3. Pick up the incorrect statement from the following: (A) Lead is the average horizontal straight distance between the borrow pit and the place of spreading soil (B) The lead is calculated for each block of the excavated area (C) The unit of lead is 50 m for a distance upto 500 m (D) The unit of lead is 1 km where the lead exceeds 2 km
4. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as 
5. In the mid-section formula (A) The mean depth is the average of depths of two consecutive sections (B) The area of mid-sections is calculated by using mean depth (C) The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections (D) All of the above
6. Brick walls are measured in sq. m if the thickness of the wall is 
7. The assumption on which the trapezoidal formula for volumes is based, is
8. Pick up the incorrect statement from the following: 
9. According to Indian Standards Institute, the actual size of modular bricks is 
10. If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by 
11. Pick up the excavation where measurements are made in square metres for payment. 
12. A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is 
13. Pick up the correct statement from the following
14. The value of 'B' of Indian type W.C. shown in the given figure is:
15. While estimating the qualities for the construction of a building, the correct metric unit is 
16. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and 
17. Pick up the correct statement from the following: 
18. The plinth area of a building not includes 
19. The rate of payment is made for 100 cu m (per % cu m) in case of 
20. The brick work is not measured in cu m in case of 
21. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 
22. The main factor to be considered while preparing a detailed estimate, is
23. While estimating a reinforced cement structure, the omitted cover of concrete is assumed 
24. The value of 'C' of Indian type W.C. shown in the given figure is:

25. The rate of an item of work depends on