Construction Project and Management Mock test – 1 || Civil Engineering Mock tests




Welcome to your Construction Project and Managment Mock test - 1
Take an exciting test in Construction and Project Management Mock tests 
You have only 20 mins to complete the test (25 Questions)
Wish you all the best!!!
Name
Email
1. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
2. In time-cost optimization of a project, crashing is done.
3. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
4. In resources levelling
5. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5,  17 and 8 days respectively, The expected time is
6. Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
7. Free float is mainly used to
8. A golden rule for the procurement of construction stones, suggests
9. The time with which direct cost does not reduce with the increase in time is known as
10. Grader is used mainly for
11. Sensitivity analysis is a study of
12. Which of the following does not represent an activity?
13. Preliminary project report for a road project must contain
14. In PERT analysis, the time estimates of activities and probability of their occurrence follow
15. At a work site, statistical quality control of concrete means
16. A critical ratio scheduling
17. For the network shown in the given figure, the expected time for the activity

18. For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
19. Critical path method
20. During the construction period, price variation clause in contracts caters to
21. Pick up the correct statement from the following
22. Which of the following earth moving machines has the shortest cycle time?
23. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
24. If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
25. Updating may result in







Share to all