Construction Project and Management Mock test - 1 || Civil Engineering Mock tests - CIVIL ENGINEERING OBJECTIVE

Construction Project and Management Mock test – 1 || Civil Engineering Mock tests




Welcome to your Construction Project and Managment Mock test - 1
Take an exciting test in Construction and Project Management Mock tests 
You have only 20 mins to complete the test (25 Questions)
Wish you all the best!!!
Name
Email
1. Pick up the correct statement from the following
2. For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
3. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
4. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5,  17 and 8 days respectively, The expected time is
5. For the network shown in the given figure, the expected time for the activity

6. In resources levelling
7. If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be
8. Grader is used mainly for
9. A critical ratio scheduling
10. During the construction period, price variation clause in contracts caters to
11. Which of the following earth moving machines has the shortest cycle time?
12. A golden rule for the procurement of construction stones, suggests
13. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
14. Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
15. In PERT analysis, the time estimates of activities and probability of their occurrence follow
16. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
17. Which of the following does not represent an activity?
18. Free float is mainly used to
19. Updating may result in
20. Critical path method
21. In time-cost optimization of a project, crashing is done.
22. The time with which direct cost does not reduce with the increase in time is known as
23. Sensitivity analysis is a study of
24. At a work site, statistical quality control of concrete means
25. Preliminary project report for a road project must contain







Share to all